NAC338.231. “Successfully completed project” defined.
Latest version.
- “Successfully completed project” means that the contract or the portion of the contract for which the prime contractor was responsible was completed:
1. Within the deadline for completion specified in the contract, as adjusted by any change order or extension of time granted; and
2. In compliance with any remaining contractual requirements, including close-out documents, within 90 days after the substantial completion of the contract.
(Added to NAC by Pub. Works Bd. by R095-04, eff. 12-15-2004)