NAC338.360. “Successfully completed project” defined.
Latest version.
- “Successfully completed project” means that the construction or the portion of the construction for which the subcontractor was responsible was completed:
1. Within the deadline for completion specified in the contract, as adjusted by any change order or extension of time granted; and
2. In compliance with any remaining contractual requirements, including close-out documents, within 90 days after substantial completion of the contract.