NAC338.360. “Successfully completed project” defined.  


Latest version.
  • “Successfully completed project” means that the construction or the portion of the construction for which the subcontractor was responsible was completed:

         1. Within the deadline for completion specified in the contract, as adjusted by any change order or extension of time granted; and

         2. In compliance with any remaining contractual requirements, including close-out documents, within 90 days after substantial completion of the contract.

     (Added to NAC by Pub. Works Bd. by R095-04, eff. 12-15-2004)