NAC341.376. Duties of contractor awarded contract for project: Recycling; submission of waste management plan and report.


Latest version.
  •      1. A contractor who is awarded a contract for the construction of a project shall:

         (a) Recycle or cause to be recycled not less than 50 percent by weight or volume of the total amount of solid waste generated by the construction of the project, including, without limitation, any associated demolition.

         (b) Submit to the Administrator a waste management plan for complying with the requirements of paragraph (a). The waste management plan must be in a form prescribed by the Administrator and include, without limitation, provisions concerning the storage, collection, recycling and disposal of all solid waste generated by the construction of the project, including, without limitation, any associated demolition.

         (c) Submit to the Administrator with each progress bill or retainage bill a waste management report documenting the contractor’s adherence to the waste management plan and measuring the contractor’s progress toward compliance with the requirements of paragraph (a).

         2. The provisions of subsection 1 must be included in:

         (a) The plans and specifications of the project submitted by a design consultant or project manager to the Administrator for approval;

         (b) The plans and specifications of a project approved by the Administrator and made available to bidders on the contract for the project pursuant to NRS 338.1385; and

         (c) The contract between the Division and the contractor for the project.

         3. As used in this section:

         (a) “Progress bill” has the meaning ascribed to it in NRS 338.415.

         (b) “Retainage bill” has the meaning ascribed to it in NRS 338.430.

     (Added to NAC by Pub. Works Bd. by R207-09, eff. 10-15-2010; A by R105-11, R106-11 & R107-11, 5-30-2012)