NAC408.527. Asphalt approaches.  


Latest version.
  •      1. The owner of property which is adjacent to a highway shall, if constructing asphalt approaches, place the paving at least 25 feet (7.6 meters) from the edge of the existing pavement or to the edge of the right-of-way if there is less than 25 feet (7.6 meters) available. The type of paving must be approved by the district engineer.

         2. Except as otherwise authorized by the district engineer, driveways, approaches and intersections of streets must be constructed pursuant to the requirements set forth in the occupancy permit.

         3. If an approach adjoins existing roadway paving, the roadway paving must be saw cut in a neat straight line the entire length of the approach, including any required taper lengths. The width of the saw cut must be at least 1 foot (300 millimeters) or as otherwise specified by the district engineer.

     (Added to NAC by Dep’t of Transportation, eff. 1-6-95; A by R135-98, 10-3-2000)