NAC445A.6664. Prescribed fees.  


Latest version.
  •      1. The Division shall charge and collect fees for its service, as follows:

         (a) Except as otherwise provided in subsection 2 of NAC 445A.6669, for reviewing an application for a permit to construct, modify or expand a public water system:

              (1) If the public water system is a community water system:

                   (I) For reviewing on-site or off-site improvement plans for the construction of a new community water system within an existing subdivision or for a new subdivision or for the modification or expansion of an existing community water system within an existing subdivision.................................... :

                              $250

                       Plus $3 for each connection for supply of water to customers.

                   (II) For reviewing plans to construct, modify or expand a community water system which is not part of a subdivision..................................................

                                300

                   (III) For reviewing plans to construct, modify or expand a treatment facility of a community water system..................................................................

    0.1 percent of the

           capital cost of                            

            the treatment

          facility, not to

          exceed $3,250

              (2) If the public water system is not a community water system, for reviewing any plans to construct, modify or expand the public water system....

                                200

         (b) For issuing an annual permit to operate a public water system:

              (1) If the system is a community water system:

    Number of connections for service to customers

                      25

    or less.....................................................................................................

                     $225

                      26

    -

    3,000......................................................................................................

                       225

    Plus 75 cents for each connection for service between 26 and 3,000 connections.

                 3,001

    -

    10,000....................................................................................................

                    2,500

    Plus 60 cents for each connection for service between 3,001 and 10,000 connections.

               10,001

    -

    50,000....................................................................................................

                    6,700

    Plus 25 cents for each connection for service between 10,001 and 50,000 connections.

               50,001

    -

    100,000..................................................................................................

                  16,700

    Plus 10 cents for each connection for service between 50,001 and 100,000 connections.

                   over

    100,000..................................................................................................

                  21,700

              (2) If the system is not a community water system and regularly serves at least 25 of the same persons for more than 6 months per year...............................................

                     225

              (3) If the system is not a community water system or a public water system that serves at least 25 of the same persons for more than 6 months per year.................

                     100

         (c) Except as otherwise provided in subsection 2, for issuing an annual permit to operate a treatment facility based on the capacity of the treatment facility as follows:

              (1) Less than 500,000 gallons per day.......................................................................

              $150

              (2) At least 500,000 gallons per day but less than 1 million gallons per day............

                250

              (3) At least 1 million gallons per day but less than 5 million gallons per day...........

             1,500

              (4) At least 5 million gallons per day but less than 10 million gallons per day.........

             2,000

              (5) At least 10 million gallons per day but less than 50 million gallons per day.......

             3,000

              (6) At least 50 million gallons per day but less than 100 million gallons per day.....

             4,000

              (7) At least 100 million gallons per day or more.......................................................

             7,500

         2. An applicant for a permit to operate a treatment facility that only provides treatment related to chlorination is not required to pay the fees set forth in paragraph (c) of subsection 1.

         3. As used in this section:

         (a) “Capital cost of the treatment facility” means the cost estimated by an engineer to construct, modify or expand the treatment facility.

         (b) “Community water system” means a public water system which:

              (1) Has at least 15 service connections used by residents for an entire year; or

              (2) Regularly serves at least 25 residents for an entire year.

     (Added to NAC by Bd. of Health, eff. 1-19-84; A 8-31-89; 12-24-90; 9-13-91; 2-20-97; R194-03, 1-22-2004; A by Environmental Comm’n by R194-08, 10-27-2009)