NAC338.092. Reports by contractors and subcontractors to Labor Commissioner: Form and contents; substantiation; provision to awarding body.  


Latest version.
  •      1. Except as otherwise provided in subsection 2, a contractor who has been awarded a contract for a public work and all subcontractors hired by the contractor shall report the name and address of each subcontractor whom the contractor or subcontractor engages for work on the public work as required pursuant to subsection 3 of NRS 338.013 on a form prescribed by the Labor Commissioner. The report must include, without limitation:

         (a) The name of the owner or principal of the subcontractor;

         (b) The telephone number and facsimile number, if any, of the subcontractor;

         (c) The scope of work to be performed by the subcontractor in connection with the public work; and

         (d) The number, if any, of the license issued to the subcontractor by the State Contractors’ Board pursuant to chapter 624 of NRS.

         2. A contractor who has been awarded a contract for a public work and all subcontractors hired by the contractor do not need to report suppliers hired by the contractor or subcontractor to the Labor Commissioner pursuant to subsection 1.

         3. A contractor engaged on a public work has the burden of proof in substantiating that he or she reported any subcontractors whom the contractor has engaged for work on the public work to the Labor Commissioner pursuant to subsection 3 of NRS 338.013.

         4. A contractor or subcontractor hired by the contractor shall provide a copy of the report to the awarding body.

         5. As used in this section, “supplier” has the meaning ascribed to it in NRS 338.010.

     (Added to NAC by Labor Comm’r by R115-01, eff. 4-5-2002; A by R207-03, 2-19-2004)