Chapter338 Public Works Projects |
CONTRACTS INVOLVING CONSTRUCTION MANAGERS AT RISK |
Contracts Between Construction Managers at Risk and Subcontractors to Provide Labor, Materials or Equipment on Projects |
NAC338.570. Applicability.
Latest version.
- The provisions of NRS 338.16991 and 338.16995 and NAC 338.550 to 338.640, inclusive, apply only to a subcontract for which the estimated value is at least 1 percent of the total estimated cost of the construction of the public work.
(Added to NAC by Pub. Works Bd. by R099-11, eff. 5-30-2012)