NAC341.105. Contract modifications.  


Latest version.
  •      1. Any change in the time, price or material set forth in a contract must be authorized in a written change order.

         2. A request by a contractor for an extension of time must be submitted in writing to the Administrator within 7 calendar days after the first occurrence of the incident causing the delay. The Administrator shall give a written acknowledgment of the receipt of such a request to the contractor.

         3. Except as otherwise provided in this subsection, if a change order which increases the price of a contract is the result of an error or omission in the plans or specifications, the architect or engineer who prepared the plans and specifications must pay the Division the estimated difference in cost between what the work would have cost in the absence of the error or omission and the actual cost. If the Administrator determines that an error or omission in the plans or specifications is minor in the context of the scope of the work, the Administrator may waive such a payment.

     [Planning Bd., Policy, Procedure and Rules §§ 3303-3308, eff. 1-20-62; A and renumbered as §§ 3301-3307, 5-3-72; A 7-16-76]—(NAC A 12-16-82; A by Pub. Works Bd., 3-17-94; R096-04, 12-15-2004; R188-07, 4-17-2008; R106-11, 5-30-2012)