NAC341.356. Determination of measures to be incorporated into project.
Latest version.
- The Administrator shall review the preliminary plans of a project and the accompanying report submitted pursuant to NAC 341.351 and determine the green building design measures that must be incorporated into the design of the project to ensure that the project will achieve the efficiencies in the use of energy and water set forth in NAC 341.346. In reaching this determination, the Administrator shall consider, in addition to the information provided by the design consultant or project manager pursuant to NAC 341.351:
1. The initial cost of the green building design measure in relation to the budget for the project set forth in the State’s capital improvement program.
2. The simple payback period of the green building design measure. The simple payback period must not be longer than 10 years, unless the Administrator determines that the use of a longer period is in the best interests of the State.
3. Any other information that the Administrator considers to be relevant to the determination.
(Added to NAC by Pub. Works Bd. by R207-09, eff. 10-15-2010; A by R105-11 & R106-11, 5-30-2012)