NAC408.333. Plans for relocation of facility.  


Latest version.
  • The plans required by paragraph (e) of subsection 2 of NAC 408.327 must:

         1. Be sufficiently detailed and complete to enable the Department to analyze the proposed work;

         2. Indicate the location, length, size, type, class and relevant operating conditions and features of design of each existing facility or proposed temporary or permanent facility, including any proposed changes, adjustments, relocations, removals and abandonments and all appropriate nomenclatures, symbols, legends, notes, color-codings and other identifications used in the plans;

         3. Indicate the project, scale of the plan and the date the plan was prepared, horizontal and, if appropriate, vertical location of the existing, proposed or temporary facility concerning the alignment of the project, geometric features, right-of-way, stationing, grades, structures and other facilities and, if applicable, access control lines;

         4. Indicate the limits of the right-of-way to be purchased from, by or on behalf of the utility, if applicable;

         5. Indicate by symbols or notes any work which will be performed solely at the utility’s expense; and

         6. Indicate each facility to be adjusted, even if reimbursement is not claimed for the facility.