NAC408.373. Cost for transportation and subsistence of employees; cost for movement of materials, supplies and equipment.  


Latest version.
  •      1. The utility’s cost for the transportation and subsistence of employees which is directly attributable to the project is reimbursable.

         2. The reasonable cost for the movement of materials, supplies and equipment to the project and the return to storage, including the cost of loading and unloading the equipment, is reimbursable.

     (Added to NAC by Dep’t of Transportation, eff. 1-6-95)