NAC414.125. Completion of project: General requirements.  


Latest version.
  •      1. Each project must be completed within 90 days after the date the application was approved by the Division, unless such time is extended by the Division based upon a showing of good cause by the requesting entity.

         2. A request for an extension of time to complete a project must be submitted to the Division in writing and approved by the Division before the expiration of the period required pursuant to subsection 1.

         3. If the period authorized for completion of a project is more than 90 days or is extended to more than 90 days, the applicant shall submit quarterly reports of each project to the Division. Every applicant shall submit a final report of each project to the Division not later than 30 days after the end of the period authorized to complete the project.

     (Added to NAC by Div. of Emergency Mgt. by R202-01, eff. 4-24-2003)