NAC439A.315. Letter of intent: Action by Department; termination.  


Latest version.
  •      1. The Department will, within 15 days after the receipt of a letter of intent, determine whether the proposed project is subject to review.

         2. If the Department determines that the proposed project would violate any condition imposed by a previously issued letter of approval, the Department will notify the applicant that the proposed project will not be considered until the condition is removed pursuant to NAC 439A.495.

         3. The Department will notify the applicant by mail of its decision. If the proposed project is subject to review, the notice will include the date by which an application must be submitted.

         4. A letter of intent is considered no longer in effect if an application is not submitted to the Department by the date specified in the notice issued pursuant to subsection 3 of this section.

     (Added to NAC by Dep’t of Human Resources, eff. 9-4-84; A 3-6-86; 11-10-87; 10-14-97)