NAC444.6894. Program for postclosure for each municipal solid waste landfill unit within Class I site.  


Latest version.
  •      1. After the closure of each municipal solid waste landfill unit of a Class I site, the owner or operator of the site shall conduct a program for postclosure for that unit. Except as otherwise provided in subsection 2, the program must be conducted for 30 years and consist of at least the following:

         (a) The integrity and effectiveness of any final cover must be maintained, including making repairs to the cover as necessary to correct the effects of settlement, subsidence, erosion or other events, and preventing runon and runoff from eroding or otherwise damaging the final cover.

         (b) The system to collect leachate must be maintained and operated in accordance with the requirements in NAC 444.681, if applicable. The solid waste management authority may allow the owner or operator to stop managing leachate if the owner or operator demonstrates that leachate no longer poses a threat to public health and safety and the environment.

         (c) The groundwater must be monitored in accordance with NAC 444.7481 to 444.7499, inclusive, and the system for monitoring the groundwater must be maintained, if applicable.

         (d) The system for monitoring gas must be maintained and operated in accordance with NAC 444.667.

         2. The length of the program for postclosure may be:

         (a) Decreased by the solid waste management authority if the owner or operator demonstrates that the reduced period is sufficient to protect public health and safety and the environment and this demonstration is approved by the solid waste management authority; or

         (b) Increased by the solid waste management authority if it determines that the lengthened period is necessary to protect public health and safety and the environment.

         3. After the completion of the program for postclosure for each municipal solid waste landfill unit at a Class I site, the owner or operator shall notify the solid waste management authority that a certification, signed by an independent licensed professional engineer and approved by the solid waste management authority verifying that the program has been completed in accordance with the plan for postclosure, has been placed in the operating record.

     (Added to NAC by Environmental Comm’n, eff. 11-8-93)