NAC445A.67571. Priority list: Submission for approval; objections to ranking of water projects.  


Latest version.
  •      1. After the Division finalizes the priority list and at least 15 days before the meeting of the Board for Financing Water Projects, the Division shall:

         (a) Submit the priority list to the Board for Financing Water Projects for approval; and

         (b) Provide a copy of the proposed final priority list to each person who submitted a preapplication to the Division.

         2. Any objection to the ranking of water projects on a proposed priority list must be filed with the Division in writing not later than 7 days before the meeting of the Board for Financing Water Projects.

         3. Objections to the proposed priority list that are not resolved by the Division before the meeting of the Board for Financing Water Projects may be made orally at the meeting of the Board for Financing Water Projects.

     (Added to NAC by Bd. of Health by R067-98, eff. 7-23-98)