NAC445A.67624. Submission of certain documentation and information to Division before commencing construction of water project; issuance of notice to proceed.  


Latest version.
  •      1. Before commencing the construction of a water project, a recipient shall submit to the Division:

         (a) Bidding schedules, estimated schedules of payment and any other information the Division deems necessary to determine the progress of the water project;

         (b) Proof of the receipt of all permits required to construct the water project;

         (c) Documentation that any procedures for purchasing and contracting required by a state agency or the Federal Government will be followed;

         (d) Agendas for any conferences regarding the water project held by the recipient before the commencement of bidding and construction;

         (e) Schedules for the design of the project, engineering, the procurement of materials, construction and any other activity related to the water project; and

         (f) Any other documents that the Division deems necessary.

         2. The recipient shall, at least 5 days before holding any conference described in paragraph (d) of subsection 1, notify the Division of the date, time and location of the conference.

         3. The recipient shall not commence the construction of the water project until receipt from the Division of a notice to proceed with the water project. The Division may issue such a notice only after:

         (a) The recipient has complied with the provisions of subsection 1 to the satisfaction of the Division; and

         (b) The Division has examined and approved the final set of plans and specifications for the water project pursuant to NAC 445A.67621.

     (Added to NAC by Bd. of Health by R067-98, eff. 7-23-98; A by Environmental Comm’n by R128-04, 2-14-2005)