NAC445A.67627. Submission of certain documents and information to Division upon completion of water project; availability of unused amount of loan.  


Latest version.
  •      1. After a recipient has completed a water project, the recipient shall submit to the Division for its approval:

         (a) A final engineering report that describes the water project as it was constructed;

         (b) Drawings of the water project as it was built which depict any material changes from the initial plans for the water project;

         (c) The dates the water project was tested, accepted and placed into service;

         (d) A notice of completion of the water project; and

         (e) A statement of the final costs for the water project.

         2. The recipient may submit its final request for disbursement of the loan only after the Division has approved the final engineering report submitted pursuant to subsection 1.

         3. Upon completion of the requirements of subsection 1 and payment of the final request submitted pursuant to subsection 2, any amount of the sum authorized for the loan that is not disbursed will be made available to other applicants who have requested financial assistance from the Account for the Revolving Fund.

     (Added to NAC by Bd. of Health by R067-98, eff. 7-23-98)