NAC445A.7675. Division authorized to bypass project on priority list in certain circumstances; notification; objection.
-
1. The Division may bypass a project on the priority list if the Division determines that the project is not ready to proceed or the applicant for the project:
(a) Withdraws the project; or
(b) Requests action to be deferred as allowed pursuant to NAC 445A.7655.
2. If the Division determines that the project is not ready to proceed, the Division shall provide notice of its determination to the applicant. After receiving notice, the applicant must respond to the Division within 30 days.
3. If the applicant files an objection in the response provided for in subsection 2 that the Division is unable to resolve, the Division shall forward the objection to the Administrator of the Division for decision pursuant to the provisions of NAC 445A.730.
(Added to NAC by Environmental Comm’n by R115-10, eff. 1-13-2011)