NAC455.165. Period for conducting excavation or demolition: Validity of notification; extension.


Latest version.
  •      1. A notification submitted by an excavator to an association for operators is valid to conduct an excavation or demolition for 28 calendar days after the date and time that the excavator provided the notification to the association for operators pursuant to the provisions of NRS 455.110.

         2. An excavator may submit a request to the association for operators to extend the period for which the excavator may engage in the excavation or demolition by an additional 28 calendar days.

         3. The association for operators shall notify the operators of subsurface installations within the affected area of the proposed excavation or demolition of the extension of time for excavation or demolition, and the period for which the excavator may engage in the excavation or demolition shall be deemed to be extended for 28 calendar days.

         4. An excavator may not request more than two extensions of the period in which the excavator is permitted to engage in an excavation or demolition pursuant to the provisions of this section. If the excavator needs additional time in which to engage in the excavation or demolition beyond the period afforded by the original notification and the subsequent extensions, the excavator shall submit a new notification to the association for operators pursuant to the provisions of NRS 455.110.

     (Added to NAC by Pub. Utilities Comm’n by R156-03, eff. 8-25-2004; A by R153-07, 1-30-2008)