NAC455C.118. Fees of Enforcement Section.  


Latest version.
  •      1. Except as otherwise provided in subsections 3 and 4, the Enforcement Section shall charge and collect the following fees:

    Certificates

    Fees

         For the issuance of a certificate....................................................................................

              $100

         For the renewal of a certificate.....................................................................................

                  50

    Power Boilers

    Fees

         If the power boiler has 250 square feet or less of heating surface:

              For the issuance of an initial operating permit, based on a preliminary and final inspection by an inspector..................................................................................

              $160

              For the annual renewal of an operating permit, based on one internal inspection and one external inspection or two external inspections....................................

                110

         If the power boiler has more than 250 square feet but not more than 750 square feet of heating surface:

              For the issuance of an initial operating permit, based on a preliminary and final inspection by an inspector..................................................................................

                160

              For the annual renewal of an operating permit, based on one internal inspection and one external inspection or two external inspections....................................

                120

         If the power boiler has more than 750 square feet of heating surface:

              For the issuance of an initial operating permit, based on a preliminary and final inspection by an inspector..................................................................................

                160

              For the annual renewal of an operating permit, based on one internal inspection and one external inspection or two external inspections....................................

                140

    Low-Pressure Steam Heating Boilers

    Fees

         If the low-pressure steam heating boiler has less than 500 square feet of heating surface:

              For the issuance of an initial operating permit, based on a preliminary and final inspection by an inspector..................................................................................

              $160

              For the annual renewal of an operating permit, based on one internal inspection and one external inspection or two external inspections....................................

                $60

         If the low-pressure steam heating boiler has 500 square feet or more of heating surface:

              For the issuance of an initial operating permit, based on a preliminary and final inspection by an inspector..................................................................................

                160

              For the annual renewal of an operating permit, based on one internal inspection and one external inspection or two external inspections....................................

                  65

    Low-Pressure Hot Water Heating Boilers

    Fees

         If the low-pressure hot water heating boiler has less than 500 square feet of heating surface:

              For the issuance of an initial operating permit, based on a preliminary and final inspection by an inspector..................................................................................

              $160

              For the biennial renewal of an operating permit, based on one internal inspection or one external inspection...................................................................................

                  60

         If the low-pressure hot water heating boiler has 500 square feet or more of heating surface:

              For the issuance of an initial operating permit, based on a preliminary and final inspection by an inspector..................................................................................

                160

              For the biennial renewal of an operating permit, based on one internal inspection or one external inspection...................................................................................

                  65

    Hot Water Supply Boilers

    Fees

         For the issuance of an initial operating permit for a hot water supply boiler, based on a preliminary and final inspection by an inspector.............................................

              $110

         For the biennial renewal of an operating permit for a hot water supply boiler, based on one internal inspection or one external inspection..............................................

                  50

    Unfired Pressure Vessels

    Fees

         For the issuance of an initial operating permit for an unfired pressure vessel, based on a preliminary and final inspection by an inspector.............................................

                $90

         For the renewal of an operating permit for an unfired pressure vessel, based on one internal inspection or one external inspection.........................................................

                  40

    Refrigeration Pressure Vessels

    Fees

         If the output capacity of the system of refrigeration is less than 100 tons:

              For the issuance of an initial operating permit for the refrigeration pressure vessel, based on a preliminary and final inspection by an inspector..................

                $80

              For the renewal of an operating permit for the refrigeration pressure vessel, based on one internal inspection or one external inspection.........................................

                  50

         If the output capacity of the system of refrigeration is 100 tons or more:

              For the issuance of an initial operating permit for the refrigeration pressure vessel, based on a preliminary and final inspection by an inspector..................

                $90

              For the renewal of an operating permit for the refrigeration pressure vessel, based on one internal inspection or one external inspection.........................................

                  60

    Boilers or Pressure Vessels Installed or Used in Single-Family Residences

    Fees

         For the preliminary and final inspections of a boiler or pressure vessel that is installed or used in a single-family residence that are required to be made at the time of installation pursuant to NAC 455C.156.....................................................

                $80

         For each subsequent inspection of the boiler or pressure vessel that is requested by the owner of the boiler or pressure vessel...............................................................

                  40

    Renewal of Operating Permits for Boilers or Pressure Vessels

    Inspected by Special Inspectors

    Fees

         For the renewal of an operating permit for a boiler or pressure vessel if the operating permit is renewed based on a report of an inspection made by a special inspector

                $20

    Special Services

    Fees

         For any services rendered by the Enforcement Section to assist a person in complying with the provisions of this chapter, including, without limitation, an inspection other than an inspection required by NAC 455C.156 and the review of plans and specifications before those plans and specifications are submitted to the Enforcement Section pursuant to NAC 455C.182:

              Per hour charge for those services provided during the first 8 hours of a day.......

                $40

              Per hour charge for those services provided after the first 8 hours of the day.......

                  60

         2. In addition to paying the fees imposed by this section for services rendered by the Enforcement Section to assist a person in complying with the provisions of this chapter, a person who requests that the Enforcement Section perform such services must pay all necessary expenses incurred by the Enforcement Section in fulfilling the request.

         3. The fees imposed by this section for operating permits or inspections of boilers or pressure vessels do not apply to boilers or pressure vessels that are owned by the United States, the State of Nevada or any political subdivision of the State of Nevada, including, without limitation, any county, city, municipality, district or commission.

         4. The fees imposed by this section for a request for services by the Enforcement Section to assist a person in complying with the provisions of this chapter and any necessary expenses incurred by the Enforcement Section in fulfilling the request will not be charged to the United States, the State of Nevada or any political subdivision of the State of Nevada, including, without limitation, any county, city, municipality, district or commission.

     (Added to NAC by Div. of Industrial Relations by R101-02, eff. 12-15-2004)