NAC459.95345. Permit required for construction; preliminary meeting with Division.  


Latest version.
  •      1. Before an owner or operator of a facility may commence the construction of a new process subject to C.A.P.P., the owner or operator must obtain a permit to construct the new process from the Division pursuant to NAC 459.95345 to 459.953467, inclusive.

         2. Before applying for a permit to construct a new process, the owner or operator of the process must meet with the Division to discuss:

         (a) The scope of the project and the applicable codes and standards relating to the design and construction of the project;

         (b) The requirements for the submission of documents; and

         (c) The schedule for the construction of the project.

     (Added to NAC by Environmental Comm’n by R041-01, eff. 10-25-2001; A by R137-04, 2-15-2005)