NAC459.95347. Maintenance and availability of information during construction activity; revised schedule for construction upon issuance of permit to construct.  


Latest version.
  •      1. During any construction activity done on a new process approved in accordance with NAC 459.953467, the owner or operator of the new process shall:

         (a) Maintain on-site:

              (1) All documents, drawings and specifications related to the construction and operation of the new process;

              (2) All records relating to inspections and testing related to the construction; and

              (3) All records relating to the construction procedure and qualifications of persons performing the construction; and

         (b) Make available such information to the Division or an authorized representative of the Division upon request by the Division or its representative.

         2. Upon the issuance of a permit to construct, the owner or operator to whom the permit is issued shall provide the Division with a revised schedule for the construction that includes the approximate timing as to when:

         (a) Concrete foundations will be poured;

         (b) The erection of the structural steel components will be commenced;

         (c) The fabrication of the process piping will be commenced;

         (d) The hydrotesting for the process piping will be commenced; and

         (e) Any other activities identified by the Division or an authorized representative of the Division will be performed or commenced.

     (Added to NAC by Environmental Comm’n by R041-01, eff. 10-25-2001; A by R137-04, 2-15-2005)