NAC459.95347. Maintenance and availability of information during construction activity; revised schedule for construction upon issuance of permit to construct.
-
1. During any construction activity done on a new process approved in accordance with NAC 459.953467, the owner or operator of the new process shall:
(a) Maintain on-site:
(1) All documents, drawings and specifications related to the construction and operation of the new process;
(2) All records relating to inspections and testing related to the construction; and
(3) All records relating to the construction procedure and qualifications of persons performing the construction; and
(b) Make available such information to the Division or an authorized representative of the Division upon request by the Division or its representative.
2. Upon the issuance of a permit to construct, the owner or operator to whom the permit is issued shall provide the Division with a revised schedule for the construction that includes the approximate timing as to when:
(a) Concrete foundations will be poured;
(b) The erection of the structural steel components will be commenced;
(c) The fabrication of the process piping will be commenced;
(d) The hydrotesting for the process piping will be commenced; and
(e) Any other activities identified by the Division or an authorized representative of the Division will be performed or commenced.
(Added to NAC by Environmental Comm’n by R041-01, eff. 10-25-2001; A by R137-04, 2-15-2005)