NAC459.95486. Prerequisites for exemption of process from C.A.P.P.; continued compliance.  


Latest version.
  •      1. A process that is otherwise subject to C.A.P.P. pursuant to subparagraph (2) of paragraph (a) of subsection 1 of NAC 459.95323 is not subject to C.A.P.P. if:

         (a) Two or more years have elapsed since the owner or operator has registered pursuant to NAC 459.95348 and completed the process hazard analysis;

         (b) The owner or operator has complied with all relevant requirements of C.A.P.P.;

         (c) The recommendations developed pursuant to subsection 8 of NAC 459.95414 are implemented; and

         (d) The State Environmental Commission has granted the exemption pursuant to NAC 459.95488.

         2. The Division shall require continued compliance with C.A.P.P. until the recommendations from the process hazard analysis are completed and the State Environmental Commission has granted the exemption pursuant to NAC 459.95488.

     (Added to NAC by Environmental Comm’n by R121-98, eff. 5-27-99; A by R137-04, 2-15-2005)