NAC461.320. Contracts for performance of inspections.
- If a manufacturer’s units of factory-built housing, manufactured buildings or modular components are to be inspected by a government agency or a private agency, the manufacturer must submit to the Division:
1. A copy of the contract between the manufacturer and the government agency or private agency or a signed statement by an officer of the government agency or the private agency that such a contract exists;
2. An explanation of the agreed method, scope and frequency of the inspections;
3. An explanation of the procedure to be used to report the results of the inspections to the Division, including copies of the forms to be used for this purpose;
4. An explanation of the procedure to be used to mark, record and ensure the correction of any variance from an approved plan; and
5. An explanation of the procedure the inspector will follow and a copy of the document he or she will use to certify that the unit, building or component complies with an approved plan and the applicable regulations.