NAC477.830. Submission of plans and specifications; corrected plans; certification of results of hydrostatic tests.  


Latest version.
  •      1. Before installing or remodeling a fire standpipe system, the owner of the system shall submit to the authority having jurisdiction:

         (a) Design specifications for the system;

         (b) A list of materials to be used in the system;

         (c) Scale drawings of the remodeling or installation which:

              (1) Can be easily reproduced; and

              (2) Are of sufficient detail to enable the authority having jurisdiction to evaluate the effectiveness of the system;

         (d) A schedule of tests required by the appropriate code; and

         (e) Calculations for the flow of water for the proposed system.

         2. When substantial change has been made in the plans approved by the authority having jurisdiction for the construction or remodeling of the system, a corrected plan depicting the system as it was built must be submitted, with the appropriate fees, to the authority having jurisdiction for approval within 10 days after the completion of the system.

         3. The results of hydrostatic tests of the system must be certified to the authority having jurisdiction and the owner in writing.

     (Added to NAC by St. Fire Marshal, eff. 3-9-89; A by R220-99, 9-25-2000; R062-04, 9-3-2004)