NAC534.4376. Instrumentation boreholes.  


Latest version.
  •      1. An instrumentation borehole may be drilled by an unlicensed well driller.

         2. The installation of monitoring instruments and simultaneous plugging must be:

         (a) Completed by a well driller who is licensed in this State; or

         (b) Supervised and documented by the responsible project geologist, hydrologist or engineer.

         3. An instrumentation borehole must be permanently plugged at the time of completion pursuant to NAC 534.4371.

         4. Documentation of each instrumentation borehole must be completed and maintained pursuant to NAC 534.4369.

     (Added to NAC by St. Engineer by R039-12, eff. 6-29-2012)