NAC534A.216. Payment of fee based on depth of well.  


Latest version.
  • Within 30 days after the completion of the construction of a geothermal well listed in this section and the removal of the drill rig from the location of the well, the person who holds a permit to drill or operate an individual geothermal well or a permit to drill or operate geothermal wells in a project area shall pay to the Division a fee based on the depth of the well according to the following schedule:

    300 to 1,000

    1,001 to 5,000

    Over 5,000

    Feet Deep

    Feet Deep

    Feet Deep

         INDUSTRIAL WELLS

              Production Well

         $1,000

          $2,000

        $2,500

              Injection Well

           1,000

            2,000

          2,500

              Observational Well

                   (larger than a 7-inch surface casing)

              500

               500

          2,500

         COMMERCIAL WELL

              200

               200

             200