NAC538.520. Firming energy.  


Latest version.
  • If the actual generation at the Hoover power plant in any year is less than that needed to fulfill the contractual entitlement of any contractor, the Commission will, at the request of the contractor, purchase energy to meet the deficiency at the contractor’s expense. If the contractor can provide firming energy from its own resources, the Commission will, annually, allow it to provide its own firming energy and will reduce proportionately the Commission’s obligation to the contractor for energy. The cost of firming energy that is provided by the Commission must be paid for in the year in which it is incurred.

     (Added to NAC by Colorado River Comm’n, eff. 9-13-85; A 11-24-87)