NAC703.185. Specific requirements for electric companies.
Latest version.
- In the case of an electric company, in addition to all other applicable requirements of NAC 703.175, an application must include:
1. Load and resource data setting forth recorded and estimated loads (energy and demands), available capacity and margins for 2 years of actual and 3 years of estimated, on the basis of an average year.
2. The effective operating capacity of generating plants which have been rated and planned additions for the next 3 years.
3. The estimated capital and operating costs of any proposed generating plant.
4. The estimated number of customers to be served and their requirements for the first 5 years of operation.
[Pub. Service Comm’n, Gen. Order 3 part § 19.020, eff. 1-1-79]