NAC704.5677. Funding plan: Information concerning costs utility will incur during term of action plan.
Latest version.
- The funding plan of a utility must set forth information concerning the costs that the utility will incur during the term of the action plan, including, without limitation:
1. The estimated costs of any construction identified in the action plan, including, without limitation:
(a) Annual flows of expenditures with allowance for money expended during construction; and
(b) Annual flows of expenditures without allowance for money expended during construction; and
2. The projected rates of escalation in costs, including, without limitation:
(a) Capital costs; and
(b) Fixed operating costs.
(Added to NAC by Pub. Utilities Comm’n by R043-08, eff. 9-18-2008)