NAC704.5677. Funding plan: Information concerning costs utility will incur during term of action plan.  


Latest version.
  • The funding plan of a utility must set forth information concerning the costs that the utility will incur during the term of the action plan, including, without limitation:

         1. The estimated costs of any construction identified in the action plan, including, without limitation:

         (a) Annual flows of expenditures with allowance for money expended during construction; and

         (b) Annual flows of expenditures without allowance for money expended during construction; and

         2. The projected rates of escalation in costs, including, without limitation:

         (a) Capital costs; and

         (b) Fixed operating costs.

     (Added to NAC by Pub. Utilities Comm’n by R043-08, eff. 9-18-2008)