NAC704.568. Action plan: General requirements.  


Latest version.
  • The action plan of a utility must include, without limitation:

         1. An introductory section that explains how the action plan relates to the long-term plans of the utility as set forth in its resource plan;

         2. A section that identifies each action for which the utility requests the approval of the Commission;

         3. A section that identifies each part of the utility’s conservation plan that the utility proposes to carry out during the term of the action plan; and

         4. A section that identifies each part of the utility’s water supply and wastewater treatment plan that the utility proposes to carry out during the term of the action plan and includes, without limitation:

         (a) For each facility for which construction will be performed during that term:

              (1) The utility’s plans for construction; and

              (2) The utility’s proposed schedule for construction, including, without limitation, the proposed dates for:

                   (I) The preparation of any environmental impact statements, if required;

                   (II) The application for and receipt of each significant permit;

                   (III) Entering into a commitment for each substantial expenditure; and

                   (IV) Placing the facility in commercial operation.

         (b) For each facility that will be acquired during that term, the proposed date for placing the facility in commercial operation.

     (Added to NAC by Pub. Utilities Comm’n by R043-08, eff. 9-18-2008)