NAC704.68064. Time for action upon request and for filing of protest.  


Latest version.
  •      1. The Commission will act upon a request filed pursuant to NAC 704.68062 within 90 days after the request is filed unless a protest is received from:

         (a) The staff of the Commission;

         (b) A person given permission to intervene by the Commission;

         (c) The Consumer’s Advocate; or

         (d) The small-scale provider of last resort that is providing the service to be reclassified.

    Ê If a protest is filed, the Commission will act upon the request within 180 days after the date on which the request is filed.

         2. A protest must be filed on or before the deadline for the filing of protests that is set forth in the notice required to be published pursuant to NAC 703.160.

     (Added to NAC by Pub. Service Comm’n, eff. 10-25-95; A by Pub. Utilities Comm’n by R186-97, 1-30-98; R211-03, 4-5-2004; R136-07, 1-30-2008)