NAC704.7982. Rate application: Statement regarding deviations from replacement projects approved in advance application.  


Latest version.
  • After the Commission has acted upon an advance application, a gas utility may deviate from one or more replacement projects approved by the Commission in the advance application if such deviation does not result in a change of more than 20 percent in the total estimated costs of the replacement projects approved by the Commission in the underlying advance application. For any such deviation, a gas utility shall provide a statement with the rate application explaining why the deviation is in the public interest.

     (Added to NAC by Pub. Utilities Comm’n by R020-13, eff. 2-26-2014)