NAC704.9395. Resource plan: Information on financial and economic characteristics of planned facilities.  


Latest version.
  • A utility’s resource plan must contain information on the financial and economic characteristics of planned facilities. The information must include:

         1. The estimated costs of construction, including:

         (a) Annual flows of expenditures with allowance for money expended during construction; and

         (b) Annual flows of expenditures without allowance for money expended during construction;

         2. The estimated costs of operation, including:

         (a) Variable costs per kilowatt-hour, with expenses for fuel and other items indicated separately; and

         (b) Fixed costs per kilowatt-hour;

         3. Net environmental costs and net economic benefits to the State;

         4. The rates of escalation of cost, including:

         (a) Capital costs;

         (b) Variable fuel costs;

         (c) Nonfuel operating costs;

         (d) Environmental costs; and

         (e) Fixed operating costs; and

         5. The average cost per kilowatt-hour at projected loads in current dollars for each year of the plan for each existing and planned facility.

     (Added to NAC by Pub. Service Comm’n, eff. 6-7-84; A 2-18-88; 3-27-92; A by Pub. Utilities Comm’n by R004-04, 5-25-2004)