NAC704A.480. Trenching.  


Latest version.
  •      1. The developer is responsible for all trenching inside the development and within the part of the extension of the telephone facilities which is within 100 feet of the boundary of the development, unless he requests the telephone company to accept responsibility for that trenching and the company so accepts. If the company so accepts, the developer shall advance to it a cash payment of the estimated cost of that trenching. After the company completes that trenching, the developer shall, upon demand, pay to it in cash any amount by which the actual cost has exceeded the advance. The company shall refund to the developer any part of the advance which exceeds the actual cost.

         2. The responsibility for trenching includes the responsibility for:

         (a) Excavating;

         (b) Breaking and repairing pavement where necessary;

         (c) Backfilling, including the supply of materials to be used as backfill;

         (d) Compacting; and

         (e) Restoring the landscaping, where applicable.

     (Added to NAC by Pub. Service Comm’n, eff. 3-15-84)