NAC704A.520. Advance of portion of estimated costs.  


Latest version.
  •      1. Except for an extension made pursuant to paragraph (a) of subsection 2 of NAC 704A.500, the developer shall pay to the telephone company, in cash before construction is begun on the extension of telephone facilities to and within a development, 50 percent of the estimated costs of constructing the extension within the development and within 100 feet of its boundary, minus any amount previously paid pursuant to subsection 3 of NAC 704A.440.

         2. The estimated costs must include the cost for preparation or the engineering drawings and designs.

         3. The estimated costs must not include the cost of:

         (a) Nonrefundable advances;

         (b) Conduits and their installation; or

         (c) Cable used to provide telephone service to persons who reside more than 100 feet from the development or the cost of installing that cable.

     (Added to NAC by Pub. Service Comm’n, eff. 3-15-84)