NAC445B.3497. Renewal of permit.


Latest version.
  •      1. All Class III operating permits must be renewed 5 years after the date of issuance.

         2. A complete application for renewal of a Class III operating permit must be submitted to the Director on the form provided by the Director with the appropriate fee at least 40 days before the expiration date of the current permit for the Class III source.

         3. An application for the renewal of a Class III operating permit must comply with all requirements for the issuance of an initial Class III operating permit as specified in NAC 445B.3487.

         4. If an application for the renewal of a Class III operating permit is submitted in accordance with subsection 2, the stationary source may continue to operate under the conditions of the existing Class III operating permit until the permit is renewed or the application for the renewal of the Class III operating permit is denied.

         5. If an application for the renewal of a Class III operating permit is not submitted in accordance with subsection 2:

         (a) The stationary source may be required to cease operation when the Class III operating permit expires; and

         (b) The owner or operator of the stationary source:

              (1) Must apply for the issuance of a new Class III operating permit pursuant to NAC 445B.3485; and

              (2) May not recommence the operation until the new Class III operating permit is issued.

         6. The fee for the issuance of a new Class III operating permit or the renewal of a Class III operating permit is specified in NAC 445B.327.

     (Added to NAC by Environmental Comm’n by R103-02, eff. 12-17-2002; A by R198-03, 4-26-2004; R191-08, 12-17-2008)