NAC461.190. Changes to approved plans.  


Latest version.
  •      1. If the Administrator or third-party reviewer has approved a plan for a model of factory-built housing, a manufactured building or a modular component, the manufacturer may not make any substantial change to the structural design or the plumbing, heating or electrical equipment or systems in that model unless he or she first obtains the Administrator’s or third-party’s approval of the proposed change.

         2. The Administrator or third-party reviewer will consider a proposed change upon receipt of:

         (a) A letter from the manufacturer in which the proposed change is described;

         (b) Two sets of plans for the proposed change; and

         (c) The applicable fee.

     [Mfd. Housing Div., Factory-built Housing Reg. § 10, eff. 8-6-82]—(NAC A by R192-05, 9-18-2006)