Nevada Administrative Code (Last Updated: January 6, 2015) |
Chapter445A Water Controls |
MINING FACILITIES |
Permits for Facilities |
NAC445A.390. Permit required; operation under existing permit.
-
1. All facilities in existence on September 1, 1989, must obtain a valid permit within 3 years after September 1, 1989.
2. After July 1, 1990, no person may begin construction of a new process component, or materially modify an existing process component, without first obtaining a permit or permit modification, or the concurrence of the Department that the construction or modification is in conformance with the existing permit.
3. The operator of a process component for which a permit has been obtained may continue to operate that process component under the conditions of the existing permit. This applies to all process components which have been reviewed and approved by the Department but have not yet been issued a permit and are either in the process of being constructed or are operating in accordance with an approval granted as of September 1, 1989. Where detailed plans have not yet been submitted to the Department for a process component that has been conceptually approved under either an existing permit or approved without an existing permit, the process component must meet the regulations in effect when construction of the new process component is initiated.
(Added to NAC by Environmental Comm’n, eff. 9-1-89)—(Substituted in revision for NAC 445.2428)