NAC445A.401. Action by Department upon application.  


Latest version.
  •      1. After determining that an application is procedurally complete, the Department shall, within 90 days, determine whether the application is technically complete, and prepare and issue:

         (a) A draft permit or a notice of intent to deny the application;

         (b) A fact sheet which:

              (1) Identifies the location of the facility;

              (2) Describes the proposed sources;

              (3) Provides a description of the facility and monitoring systems;

              (4) Identifies the probable receiving water; and

              (5) Describes the procedures for public comment; and

         (c) A public notice for each draft permit or intent to deny an application for a permit to construct, operate and close a mining and beneficiation facility.

         2. The 90-day time for action by the Department may be extended by the amount of time necessary for the applicant to submit additional information necessary to make the application technically complete.

     (Added to NAC by Environmental Comm’n, eff. 9-1-89)—(Substituted in revision for NAC 445.24302)