NAC445A.409. Issuance and maintenance of permit; maximum term and renewal of permit.  


Latest version.
  •      1. If an application is approved, a single permit must be issued for the construction, operation and closure of the facility. A valid permit must be maintained until permanent closure is complete.

         2. A permit may be issued for a maximum term of 5 years, at which time the holder of the permit may apply for renewal.

     (Added to NAC by Environmental Comm’n, eff. 9-1-89)—(Substituted in revision for NAC 445.24318)