NAC445A.427. Duties of holder of permit upon construction or modification of process component.  


Latest version.
  • Within 30 days after completing construction on a new process component or materially modifying an existing process component, the holder of the permit shall submit to the Department:

         1. As-built drawings of the process component;

         2. A summary of the quality control procedures which were carried out during construction; and

         3. The final operating plans required by NAC 445A.398 which have been revised to reflect modifications made during construction.