NAC445A.427. Duties of holder of permit upon construction or modification of process component.
Latest version.
- Within 30 days after completing construction on a new process component or materially modifying an existing process component, the holder of the permit shall submit to the Department:
1. As-built drawings of the process component;
2. A summary of the quality control procedures which were carried out during construction; and
3. The final operating plans required by NAC 445A.398 which have been revised to reflect modifications made during construction.
(Added to NAC by Environmental Comm’n, eff. 9-1-89)—(Substituted in revision for NAC 445.24348)