NAC445A.67625. Provision of certain documentation and reports to Division during construction of water project.  


Latest version.
  • During the construction of a water project, a recipient shall provide to the Division:

         1. Such documentation as the Division deems necessary to determine compliance with the loan contract; and

         2. Monthly reports regarding the progress of the construction of the water project, each of which must:

         (a) Include a current budget for the completion of the water project which accurately reflects:

              (1) Any costs incurred up to the date of the report;

              (2) The anticipated costs to complete the water project; and

              (3) The status of available funding;

         (b) Identify each major change to any schedule for the water project and describe each reason for that change; and

         (c) Be accompanied by copies of any change orders affecting the scope or cost of any components of the water project.

     (Added to NAC by Bd. of Health by R067-98, eff. 7-23-98)