NAC445A.900. Action by Director on plan for corrective action.  


Latest version.
  •      1. If a plan of corrective action has been determined by the Director to be adequate, the Director shall incorporate it into the permit as a condition.

         2. If the Director’s review of the plan indicates that the plan is inadequate pursuant to NAC 445A.899, the Director shall require the applicant to revise the plan, prescribe a plan for corrective action and a schedule for compliance as a condition of the permit or deny the application.

     (Added to NAC by Environmental Comm’n, eff. 7-22-87; A 10-21-87)—(Substituted in revision for NAC 445.42655)