Nevada Administrative Code (Last Updated: January 6, 2015) |
Chapter459 Hazardous Materials |
REGULATION OF HIGHLY HAZARDOUS SUBSTANCES AND EXPLOSIVES |
Permits |
NAC459.953465. Notice of receipt of application for permit to construct; period for public comment; action by Division after period of public comment.
-
1. Upon determining that an application for a permit to construct a new process is complete, the Division shall issue a notice of its receipt of the application. The notice must:
(a) Be sent to the applicant and the local governing body in the area in which the new process is to be located, and be published in a newspaper of general circulation for the area in which the process is to be located; and
(b) Summarize the review to be conducted by the Division on the application for the permit to construct and state that the following information will be available for public review:
(1) The registration submitted pursuant to NAC 459.953451;
(2) The coordinated emergency plan document;
(3) The site plan; and
(4) A copy of the conditional use permit.
2. The period for public comment must be 30 days and commences on the date on which the notice is published in the newspaper.
3. Not later than 15 days after the date on which the period for public comment concerning an application for a permit to construct closes, the Division may, after considering the documents that are part of the application, require further modifications if such modifications are determined necessary to satisfy the requirements set forth in NAC 459.953467 for issuing a permit to construct.
(Added to NAC by Environmental Comm’n by R041-01, eff. 10-25-2001; A by R137-04, 2-15-2005)