NAC538.570. Meters.


Latest version.
  •      1. A contractor shall provide suitable equipment for metering power allocated to it pursuant to NAC 538.340 to 538.740, inclusive, to provide data as required by the Executive Director of the Commission.

         2. The equipment for metering must be installed at the contractor’s designated points for measuring and must be maintained, tested and repaired as required by the Executive Director of the Commission.

         3. The Executive Director of the Commission shall provide for the full adjustment of claims between the Commission and a contractor arising from the inaccuracy of a meter.

     (Added to NAC by Colorado River Comm’n, eff. 9-13-85; A 11-24-87; R123-00, 2-15-2001)