NAC445A.5403. Approval of project: Prerequisites; effective period; revocation.  


Latest version.
  •      1. The Division or the appropriate district board of health shall not approve a project for a facility to treat groundwater unless the application for approval of the water project demonstrates that the water project will comply with the applicable provisions of NAC 445A.54022 to 445A.5405, inclusive.

         2. Approval of a water project is effective for 1 year, except that the Division or the appropriate district board of health may extend this period in 1 year increments if:

         (a) Work is being performed on the water project; and

         (b) The Division or the appropriate district board of health receives a schedule of work and periodic updates on the progress of the water project.

         3. The Division or the appropriate district board of health shall revoke its approval of a water project if work on the water project:

         (a) Does not commence within 1 year after the approval of the water project becomes effective; or

         (b) Ceases for a continuous period of 1 year.

     (Added to NAC by Environmental Comm’n by R126-05, eff. 10-31-2005)